ATI 2x 5TPH System

Date: May 2018 ~ August 2019

Project Location: Philippines

Application: Industrial Power Plant Usage

Customer: Engineering Company

Capacity: 2x 125TPH MMF & 2x 5TPH Double Pass RO plus EDI

Treatment Process: MMF - RO - EDI

Special Requirements

Difficulties and Solutions

"Difficulty: Power plants require water with extremely low conductivity and minimal silica levels to protect sensitive equipment like boilers and turbines. Meeting these standards while ensuring system reliability and efficiency was critical.

Solution: Instead of a single 10 m³/h system, we designed two parallel 5 m³/h systems. This ensures uninterrupted operation; if one unit requires maintenance, the other can continue to meet the plant’s needs. The modular design also allows for easier maintenance. "

Date: May 2018 ~ August 2019

Project Location: Philippines

Application: Industrial Power Plant Usage

Customer: Engineering Company

Capacity: 2x 125TPH MMF & 2x 5TPH Double Pass RO plus EDI

Treatment Process: MMF - RO - EDI

Special Requirements

Difficulties and Solutions

"Difficulty: Power plants require water with extremely low conductivity and minimal silica levels to protect sensitive equipment like boilers and turbines. Meeting these standards while ensuring system reliability and efficiency was critical.

Solution: Instead of a single 10 m³/h system, we designed two parallel 5 m³/h systems. This ensures uninterrupted operation; if one unit requires maintenance, the other can continue to meet the plant’s needs. The modular design also allows for easier maintenance. "